Bizen

Okayama, Japan

111.8

Repurposing a closed golf course in Okayama Prefecture, Bizen had to overcome natural disasters and prefectural regulation changes by applying for a partial Commercial Operation Date as a result of persistent negotiations with the government and the utility company.

Bizen

Okayama, Japan

111.8

Offtaker of Electricity

Chugoku Electric Power Company

Scale of Power Generation

111.8 MWdc

Location

Wake-cho, Okayama-ken

EPC Contractor

JX Engineering Corp.
RAYS NEXT Co., Ltd.

Project Finance

Other Syndicate Banks

Date of Facility Certification

September 20, 2016

Commencement of Construction

July 2018

Date of Commercial Operation

December 30, 2020

Status

Operational