Hosoe
Offtaker of Electricity
Kyushu Electric Power Company
Scale of Power Generation
96.2 MWdc
Location
Miyazaki-shi, Miyazaki-ken
EPC Contractor
Toyo Engineering Corp.
Project Finance
MUFG Bank, Ltd.,
10 Syndication Banks
Date of Facility Certification (METI)
January 25, 2013
Commencement of Construction
March 2015
Date of Commercial Operation
February 19, 2018
Status
In operation

Currently the fourth largest operating plant in Japan requiring the movement of an incredible 5.6 million cubic meters of earth, Hosoe took almost three years to construct.